Wave buoy location | 52° 49'.58N 001° 32'.97E |
WMO code | 6201051 |
Approximate water depth | 10 m |
Approximate spring tidal range | 2.6 m |
Storm alert threshold | 2.66 m |
Meteorological station location | 52° 48'.80N 001° 33'.37E |
Wave parameters are recorded using a Datawell Directional WaveRider Mk III buoy. The buoy was deployed on 04 September 2012, at which time the magnetic declination at the site was 0.83° West, changing by 0.17° East per year. Wave direction is reported following the nautical convention, meaning that the direction is where the waves come from, measured clockwise from magnetic north.
30/10/2024 | Scheduled service |
27/09/2024 | The met station computer needs to be replaced. A site visit will take place as soon as feasible. The computer was replaced on 30/10/2024 |
29/08/2024 | Scheduled service of the met station. |
11/05/2024 | Scheduled service |
26/03/2024 | Scheduled service of the met station. |
08/09/2023 | The buoy was serviced and redeployed. |
03/08/2023 | Scheduled service of the met station. |
29/06/2023 | They buoy has been recovered temporarily due to an ongoing geophysical survey in the immediate area. The buoy will be redeployed as soon as possible. |
28/04/2023 | Communications from the met station have been interrupted, an investigation is underway. |
14/11/2022 | Scheduled service |
30/08/2022 | Scheduled service of the met station. |
29/06/2022 | The buoy was switched to Iridium at midnight. |
20/05/2022 | Scheduled service of the DWR. |
04/02/2022 | Scheduled service of the met station. |
08/12/2021 | The buoy will be switched to iridium at midnight tonight. |
07/12/2021 | The receiver station for the buoy is offline due to a major BT service outage. Remedial works are ongoing and expected to be completed by 09:00 on Friday 10 December. |
13/08/2021 | Scheduled service |
02/03/2021 | Scheduled service |
26/09/2020 | The shore station has suffered a power cut. Repairs are scheduled for the weekend. |
17/07/2020 | Scheduled service |
12/01/2020 | Scheduled service |
26/11/2019 | A BT engineer has attended the site to upgrade to fibreoptics. The line speed has increased greatly since. |
05/09/2019 | Shore statoin visited to install a new computer. |
19/06/2019 | The buoy was swapped serviced to remedy a break in the HF antenna. |
04/06/2019 | Shore station visited to enable remote power cycling of the router. |
14/05/2019 | Shore station visited to replace RXC. |
22/03/2019 | Scheduled service |
30/11/2018 | Shore station visited to enable HF communication. |
15/08/2018 | Scheduled service |